5000 ton/gün Kapasiteli Klinker Üretim Hattı

Proje Adı : 5000 ton/gün Kapasiteli Klinker Üretim Hattı
İşveren Adı : Üstyapı İnşaat ve Madencilik A.Ş. ANKARA/TÜRKİYE
Sözleşme Tarihi : 13.10.2014
Tamamlanma Süresi : 20 Ay
Projenin Kapsamı :
  • Polysius Raw Mill Unit ᴓ 5,2 m x 13m; 220 tph 
  • Khd Rotary Kiln ᴓ 4,65 m x 59 m; 5000 tpd
  • Chinese Coal Mill; 5 tph
  • Fls Tirax Coal Mill; ᴓ 3,4 m x 8,5 m 10 tph
  • Norm Stacker & Reclaimer
  • Local Coal Stockhall
  • Fabrication of the Steel Structure    :  2 500 t
  • Fabrication of the Technological Equipments   :  1 850 t
  • (Casing of the filters ,hoppers, gas ducts, coolin tower ,
    chimney e.t.c. )
  • Fabrication of the Mechanical Equipments   : 1 050 t  (Raw and Coal mill separators and their accessories, base frame of the rotary kiln, their accessories, valves ,expansion joints, air slides and e.t.c.) 
  • Total weight of the fabrication works :  5 400 t
  • Total weight of the installation works :  7 050 t